Index
Summary of arbitration
Final Result
Records of parties pre-arbitration
Complete arbitration records
Summary of arbitration:
1) On Arbitration Response Id: 366,119 Colin
Behr was given the choice by the arbitrator Amanda, to either claim insufficient
progress (in which case RAC would test and award funds appropriately) or
continue working with BGeorge. He chose to continue working.
2) A conflict arose between Colin Behr and BGeorge during this process of
agreeing upon the deadline and requirements. As a result the arbitration was
transferred from Amanda to Rafeek (a technical arbitrator).
3) Rafeek then attempted to resolve this conflict. He asked for
information several times regarding the flaw list from Colin Behr, who did not
provide it to him. Colin Behr was forfeited for non-response.
4) Colin Behr requested a review from a senior arbitrator. Ian (the senior
arbitrator) reviewed the forfeiture and overruled it because he determined that
miscommunication caused #3 to occur (not the deliberate lack of following of
instructions, as Rafeek has thought). This occurred on Arbitration
Response Id 419,761.
5) The arbitration was restarted.
6) On Arbitration Response Id: 422,289,
Colin Behr was reminded that the 3 day deadline
for responses was in effect. This meant he needed to respond to questions
strictly within 3 days or he would forfeit. This warning was given to him
as he had violated the 3 day deadline three times previously: once on this
arbitration and twice on a previous arbitration. He was warned that a 3rd
exception would not be given and that forfeiture would be strictly enforced.
7) Colin Behr did not respond with needed information by his deadline of
Friday Sep 8, 2006 2:00:11 AM, and was forfeited.
8) Colin Behr requested and received a review on this forfeiture. Michele
(the senior arbitrator) reviewed it and found the forfeiture was correct.
It was not overturned.
9) After forfeiture, RAC testing determined that 85% of the funds were completed
by BGeorge ($255). The remainder ($45) was returned to Colin Behr.
Records of parties
pre-arbitration:
Buyer: Colin Behr:
8 successfully completed projects. 1 lost arbitrations:

This previous lost arbitration was also due to Colin Behr not responding in the
timeframe he agreed. Like this arbitration, he received a reminder and an
extension...both of which he ignored...and led to his forfeiture.
Coder: BGeorge:
113 successfully completed projects. 5 lost arbitrations:
(Since
record is very long...complete
record is here).
Complete arbitration
records
Due to the review, this arbitration was split into 2 separate arbitrations.
Original bid request
Onsite communication
Arbitration
Part 1
Arbitration
Part 2